Programmed Maintenance Follow on Tasks

17/6/2019

0 Comments

 
On many of the PFI contracts for which we provide performance management services, we see an absence of self-reporting of issues to the Help Desk. This is particularly prevalent in tasks that are identified through planned maintenance activities. Here we discuss the background to the issue and what your Project Company and service providers should be doing.

In the vast majority of PFI contracts there is an obligation to agree an annual planned maintenance programme, often referred to as the Schedule of Programmed Maintenance. These are pre-approved activities that the Hard FM contractor will carry out over the course of the year and for which they traditionally receive an Excusing Cause, in other words they are relieved from their obligation to maintain the Availability of areas whilst undertaking the planned maintenance activity without penalty. 

Programme descriptions are often cursory in nature, therefore to understand the true nature of the planned tasks that sit behind an activity, it is often necessary to ask to review the ‘task sheets’ that sit within the CAFM system and which stipulate the individual tasks that make up the planned activity. 

The important point to remember is that the relief that the Excusing Cause provides is limited to the planned works on the programme, not consequential works that are discovered whilst undertaking the planned maintenance activities. 

So, taking an example of fixed wire testing, the planned activity is to conduct the test. If the test results show elements of the electrical system that are not compliant, this constitutes a fault and should be reported to the Help Desk by your service provider. Thereafter, it should be responded to and rectified in accordance with the requirements of the contract. 

It appears to be common practice on some contracts for service providers to utilise systems outside of the Help Desk to manage the need for consequential maintenance activities that are necessary to address faults discovered as a result of planned maintenance activities. It is our belief that this is primarily an attempt to avoid the maintenance works being subject to the requirements under the contract terms to respond to and rectify faults within specific timeframes. 

There are clearly examples where future maintenance needs identified as a result of planned maintenance activities do not represent faults. For instance a lift inspection may identify that a component is nearing the end of its useful life and, whilst still compliant at the date of the inspection, may need replacing within the next 6 months. It is perfectly acceptable practice in this regard for your Project Co to update their planned maintenance programme to pick up this requirement.

What is not acceptable, however, is for issues that are faults (ie issues that do not meet the contract standards) to be programmed at a future point or not logged on the Help Desk. 

If you think that your service providers may be operating outside of the approach outlined above, please do not hesitate to contact us for further advice. 

0 Comments

    Authors

    The authors have experience of more than 100 PFI projects in multiple sectors.

    Archives

    March 2021
    April 2020
    March 2020
    October 2019
    September 2019
    June 2019
    March 2019
    May 2018
    June 2017
    October 2015
    July 2015
    June 2015
    April 2015
    March 2015
    February 2015
    January 2015
    October 2014
    August 2014
    July 2014
    June 2014
    May 2014
    October 2013
    July 2013
    June 2013
    May 2013

    Categories

    All
    Charitable Donation
    Code Of Conduct
    Contracts
    Covid 19
    Covid-19
    Damage
    Honesty
    Insurance
    Monthly Reports
    News
    PF2
    Pfi
    PPM
    Profit
    Public Sector
    Relationships
    Savings
    Secondary Market
    Special Purpose Companies
    Vacancy

    RSS Feed

P2G LLP
A Social Enterprise Partnership
Registered in England & Wales
No. OC375527
​P2G Contract Support LLP
Registered in England & Wales
No. OC419519